News from our newspaper (Reporter Wen Ziyu) On the coast of the South China Sea, the second phase of my country's first deep-water high-pressure project "Shenhai No. 1" is in full swing.

Nearly 70 kilometers to the northeast, the "Shenhai No. 1" production platform stands majestically, continuously producing natural gas from the depth of the formation at a water depth of 1,500 meters.

  "The second phase of the 'Deep Sea No. 1' project, which was drilled at the end of last year, is a key project for CNOOC to increase reserves and production. After the project is completed, it will provide a strong guarantee for the economic development of the Guangdong-Hong Kong-Macao Greater Bay Area and the livelihood of the people." In order to ensure continuous operation Operation, safety and efficiency, the CNOOC Discipline Inspection and Supervision Team urges the discipline inspection agencies of the subordinate units to actively extend the supervision tentacles, formulate supervision work ledgers according to the project promotion plan and key nodes, refine the supervision tasks, and effectively promote the resolution of delayed arrival of key procurement packages for the project , Inadequate customs clearance of foreign large-scale operating ships and other issues.

At the same time, follow up and supervise by attending project team meetings, listening to reports, consulting weekly and monthly reports, and sinking front-line research and interviews to find problems in a timely manner and promote rectification.

  At present, various key projects and projects of central enterprises are gradually resuming work and production, accelerating the pace of economic recovery.

Disciplinary inspection and supervision agencies at all levels of central enterprises keep a close eye on the key nodes of the project start, supervise the difficult and blocked points in the operation, and press the "fast forward button" to help the construction of key projects.

  "The China Petroleum Disciplinary Inspection and Supervision Team keeps an eye on the resumption of production and stable operation of major projects, deploys and conducts special supervision, guides the company's discipline inspection committee to give full play to the advantages of close supervision, coordinates and promotes various supervision and linkages, and supervises at the front to break through 'blocking points' and conduct precise supervision Remove the 'blockage' and ensure the safe and stable operation of the two major industrial chains of oil and gas." Said the comrade in charge of the discipline inspection and supervision team.

  Guangdong Petrochemical Refining and Chemical Integration Project is a key refining and chemical project with the largest one-time investment of PetroChina. It is currently the only refining and chemical base in China that can process all low-quality heavy oil, and it bears the major responsibility of promoting high-quality development of regional industries.

The Disciplinary Inspection and Supervision Team of PetroChina urged the Disciplinary Committee of Guangdong Petrochemical Company to focus on the high-quality test run of the project and set up a supervision and guarantee team to carry out supervision and inspection at the front line. 57 problems were found and rectified, and 35 suggestions were put forward.

At present, the refining process of the whole project has been basically opened up, the chemical plant is ready for feeding materials, and the countdown to commissioning and commissioning has entered.

  "As a major national nuclear environmental protection scientific research project, China's Beishan Underground Laboratory (Longtai Project) will become the world's largest underground laboratory with the most complete functions and the most extensive participation after it is fully completed. The R&D and application of disposal technology is of great significance.” The comrades in charge of the Disciplinary Inspection and Supervision Group of my country National Nuclear Corporation introduced that the construction of Longtai Project has entered the construction stage. Supervise and supervise the handling of key issues to urge all parties to fulfill their responsibilities.

During the Spring Festival, the supervision and linkage working group went to the site, combined with supervision and assistance, adhered to the front line of project construction with the participating personnel, seized the start, ensured that the main project construction "doesn't close", and played a leading role in the resumption of production of major projects.

  In Dongying, Shandong, 10 brand-new silver storage tanks of the new crude oil depot of Sinopec Shengli Oilfield gleamed in the sunlight.

Sinopec's discipline inspection and supervision team carried out a special inspection on the Dongying crude oil depot relocation project, established a joint inspection team, and refined and formed a list of 92 key inspection tasks in 17 aspects, helping to build a 314-day safe and high-quality building that is intelligent, efficient, multi-energy complementary, and environmentally friendly. Friendly benchmark oil depot.

  "We successively organized and carried out special supervision on 7 key projects including Shengli Oilfield Dongying Crude Oil Depot Relocation, Tianjin Nangang Ethylene, Xinjiang Kuqa Green Hydrogen, and Baling Petrochemical Caprolactam, aiming at project investment control, engineering management, safety and environmental protection, material procurement, The 18 key items such as the construction of a clean government will be supervised in the form of "online + offline" to help resume work and production at full capacity." Said the responsible comrade of the discipline inspection and supervision team of Sinopec.